The equation of towers height calculation carryingpower transmission lines at their intersection with engineering installation is one of the methods of designing power nets,the solution of which depends on the traditional method for calculating conductors coordinates. Sometimes this problem becomes so complicated or impossible to solve, therefore, we have to use the space solution mainly when the wind direction made an angle with these transmission lines and the points of hanging height difference. In this case it is better to use the vector method which we used at the present work. We used a mathematical model to calculate the minimum point coordination of the transmission lines curves and the minimum distance between the engineering installation and that of these transmission lines, and the suitable carrying towers heights, a cording to the permissible electrical equipment laws. So we could find the suitable towers height coordinates by using the C++ applicable program. Calculation errors between traditional and vector method reaches high value which increases with the slope angle increasing of conductors.

References used
LEI, H.; LIMCING, W.; GUANZHICHENG. Design of interphase composite spacer for 500 Kv compute Transmission line.XIXthed, international symposium on high voltage engineering Tsinghua University, Beijing, China,2005.
HUSAIN, A. Electrical power systems. Delhi, India,1998, 270
BCHINAKOVICH, A.D. Mechanical calculation power transmission lines. Industrial press, USSR, 1990,284
SCH LABBACH S; ROFASILI,K.H. Power system Engineering. WILGY-VCH Verlag G mbh & COKGTA,FRG,2008,350
GRIGSBY,L.L. Electric power generation, Transmission, and Distribution CRC Press, USA,2007,600
الحساب الستاتيكي لقضبان التجميع اللدنة لمحطات توزيع الطاقة المكشوفة .مجلة جامعة حلب,سوريا,سلسلة العلوم الهندسية,العدد2012,103,18
الميرمي سعيد . مبادئ التحليل العددي.الدار العربية للكتاب,ليبيا,1994,288
NAKAMURA .Applied Numerical Methods in shoichiro. Ohio University,USA,2000,604
BKMETOVE, B,M. Span length approximation effect in the wind power effect calculation of electric power transmission lines . N 4, power press, Moscow, USSR,1984,52-53
COLDVEIN, E. The vectorial analysis and the field theory. The Sciences, Linengrad, Moscow,USSR,1988,180
KISSLMAN, L. M. Electric power Conductors Calculation Methods in the Mountains Zones. Power press, Moscow, USSR,1990,184
rate research

Read More

يقسم الكتاب إلى: الشبكات الكهربائية الموحدة. محطات التوليد الحرارية. القسم الكهربائي في محطات التوليد. محطات التوليد النووية. محطات التوليد المائية. محطات التوليد بالطاقة المتجددة. أساليب نقل الطاقة الكهربائية. الأبراج الهوائية لنقل القوى. ع وازل خطوط النقل. تمثيل خطوط النقل. مقدمة عامة عن محطات التحويل. المعدات الرئيسية في محطات التحويل. ترتيبات قضبان التوزيع. تأريض محطات التحويل. الأنظمة المساعدة في محطات التحويل. ملامح تخطيط شبكات التوزيع. أمثلة تطبيقية لتخطيط شبكات الجهد المتوسط. العناصر الأساسية بشبكة التوزيع. أنظمة التغذية في الجهد المتوسط. شبكات الجهد المتوسط الهوائية. دراسات هامة في شبكات التوزيع. المواد المستخدمة في صناعة الكابلات. تركيب الكابلات. الخواص الكهربائية للكابلات. اكتشاف أعطال الكابلات. الهزات العابرة في نظم القوة الكهربائية. استقرار منظومة القوى الكهربائية. التوافقيات في الشبكات الكهربائية.
This research present broadband over power lines (BPL) technology as an effective option for Syrian Arab republic since this technology basically based on existing network which supply the electricity to the public use.
This paper shows a new approach to determine the presence of defects and to classify the defect type online based on Artificial Neural Networks (ANNs) in electrical power system transmission lines. This algorithm uses current and voltage signals samp led at 1 KHz as an input for the proposed ANNs without the involvement of a moving data window, so input data will be processed as a string of data. The model depends on three neural networks one for each phase and another fourth neural network for the involvement of the ground during the fault. Response time of the classifier is less than 5 ms. Moreover modern power system requires a fast, robust and accurate technique for online processing. Simulation studies show that the proposed technique is able to distinguish the fault type very accurate. Also this technique succeeded in determining of all defect types under all system conditions, so it is 100 percent accurate, so it is suitable for online application.
High Voltage Direct Current systems have been used for transporting electrical energy for very long distances, at high voltages (100- 1000 kv). On utilize thyristorized or transistorized power converters, one converter is working as rectifier at s ending side, and the other is working as inverter at receiving side. Back to Back Converters are used also where the rectifier and inverter are at the same station, transmission line has hundreds of meters as long. In our model we used non controlled three phase rectifier as sending station and controlled three phase bridge as receiving station (Graitze).
Our research includes the transmission mechanism of the wind turbine and the calculation of losses, such as loss of mechanical ventilation and friction loss and the loss of lubrication between the gear teeth design. Aims and access to high reliabili ty work and thus obtain high efficiency and taking advantage of electronic programs, We observed that each type of previous losses have an impact on the overall loss of Gearbox, Depending on the working conditions, For example, at low speeds, loss of friction between the teeth is a great percentage of the total loss, And thus controls the overall efficiency of the transport system, while at high speeds noticed this low percentage of loss, while the loss of lubrication and ventilation rate rose.