Do you want to publish a course? Click here

Development a Method to Analyze and Risk Management in Dams Projects in Syria

تطوير منهجية لتحليل و إدارة مخاطر مشاريع السدود في سورية

2017   1   148   0 ( 0 )
 Publication date 2015
and research's language is العربية
 Created by Shamra Editor




Ask ChatGPT about the research

The Dams are large and complex projects, and are generally characterized by the enormous cost of implementation in some cases, and the length of the implementation period, are rarely carried out a dam in Syria within the estimated plan which developed his of the cost and time, this is due to the risks that intercepted projects during the implementation phase and directly influenced the basic project objectives ( cost and time and quality). This research experiences to the reality of the implementation of the late dams, through undertake a study the risks suffered by the implementation of sector and influenced the basic objectives of the project (cost - time - quality), through a field survey study includes more than thirty-five dams in Syria. For this purpose have been used survey was distributed to a slice of experts and technicians in the form of dams, has enabled to obtain a list of the risks faced by the implementation of dams in addition to the assessment, In an attempt to develop a scientific methodology to analyze and manage the risks of dam projects by assessing the probability of their occurrence and their impact on the objectives of the project in the event of occurrence, with introduce a new standard for evaluating a detection / control, As per the approach to FMEA /Failure Mode and Effect Analysis/ and incorporate logic fuzzy, and arrange those risks according the Risk Criticality Number (RCN) for each risk early in order be sensitive to them than we can handled properly with proposing appropriate response strategies.


Artificial intelligence review:
Research summary
تتناول هذه الدراسة تطوير منهجية لتحليل وإدارة مخاطر مشاريع السدود في سوريا. تعتبر السدود من المشاريع الضخمة والمعقدة التي تتطلب وقتًا طويلًا وكلفة عالية للتنفيذ، وغالبًا ما تتجاوز هذه المشاريع التقديرات الزمنية والمالية الموضوعة لها بسبب المخاطر التي تواجهها. يشمل البحث دراسة ميدانية لأكثر من 35 سدًا منفذًا في سوريا، حيث تم جمع البيانات من خلال استبيانات وزعت على الخبراء والفنيين في مجال السدود. تم استخدام منهجية تحليل نموذج الفشل وآثاره (FMEA) مع دمج المنطق الضبابي لتقييم المخاطر وتصنيفها حسب درجة أهميتها (RCN). تهدف هذه المنهجية إلى التنبيه المبكر للمخاطر والتعامل معها بفعالية من خلال اقتراح استراتيجيات رد مناسبة. أظهرت النتائج أن المخاطر الأكثر أهمية تتعلق بضعف التحريات الجيولوجية وانحراف الكلفة بشكل كبير، بينما كانت المخاطر الأقل أهمية تتعلق بنقص المهارات الفنية للعمال وضعف الاتصال بين أطراف المشروع. توصي الدراسة بتطوير قدرات فرق إدارة المشاريع وتدريبهم على إدارة المخاطر، وتوثيق البيانات بشكل أفضل، واستخدام برنامج RA لتحليل المخاطر في مشاريع السدود.
Critical review
تعتبر هذه الدراسة خطوة مهمة نحو تحسين إدارة مشاريع السدود في سوريا، إلا أنها تواجه بعض التحديات. من أبرز هذه التحديات هو الاعتماد الكبير على الخبرة الشخصية للخبراء في تقييم المخاطر، مما قد يؤدي إلى تحيزات شخصية. كما أن استخدام المنطق الضبابي قد يكون معقدًا ويتطلب تدريبًا مكثفًا للفرق العاملة. بالإضافة إلى ذلك، قد تكون البيانات المجمعة من المشاريع السابقة غير كافية أو غير دقيقة بما يكفي لتقديم تقييم شامل للمخاطر. من المهم أيضًا مراعاة أن الظروف السياسية والاقتصادية المتغيرة في سوريا قد تؤثر بشكل كبير على تنفيذ هذه المنهجية. على الرغم من هذه التحديات، فإن الدراسة تقدم إطارًا قويًا يمكن تطويره وتحسينه بمرور الوقت.
Questions related to the research
  1. ما هي المنهجية المستخدمة في تحليل وإدارة مخاطر مشاريع السدود في هذه الدراسة؟

    استخدمت الدراسة منهجية تحليل نموذج الفشل وآثاره (FMEA) مع دمج المنطق الضبابي لتقييم المخاطر وتصنيفها حسب درجة أهميتها (RCN).

  2. ما هي المخاطر الأكثر أهمية التي تم تحديدها في الدراسة؟

    أظهرت الدراسة أن المخاطر الأكثر أهمية تتعلق بضعف التحريات الجيولوجية وانحراف الكلفة بشكل كبير.

  3. ما هي التوصيات التي قدمتها الدراسة لتحسين إدارة مخاطر مشاريع السدود؟

    توصي الدراسة بتطوير قدرات فرق إدارة المشاريع وتدريبهم على إدارة المخاطر، وتوثيق البيانات بشكل أفضل، واستخدام برنامج RA لتحليل المخاطر في مشاريع السدود.

  4. ما هي التحديات التي تواجه تنفيذ هذه المنهجية في سوريا؟

    تواجه المنهجية تحديات مثل الاعتماد الكبير على الخبرة الشخصية للخبراء، تعقيد استخدام المنطق الضبابي، وعدم كفاية أو دقة البيانات المجمعة من المشاريع السابقة، بالإضافة إلى الظروف السياسية والاقتصادية المتغيرة في سوريا.


References used
JALAL, M. B.; GHODDOSI, P.; HOSSEINALIPOUR, H. -Development of a Fuzzy Risk Assessment and Contractual Allocation Model for Iran's Dam Construction Projects, Advancing and Integrating Construction Education. 2008, 366-376
SAID, B.-A New Approach of Project Cost Overrun and Contingency Management. OCRI Partnership Conferences Series Process &Project Management Ottawa, 2005
The report of the world commission on Dams (WCD).- Dams and Development, London and sterling, VA. , 2000
rate research

Read More

Construction projects are subject to risks and uncertainties which affect project targets (cost, time, quality and safety). This paper reviews risks and their effects on construction projects in Syria, and it aims to develop risk management framew ork. In this work, risks in construction projects have been defined based on the literature review and interviews of some experts in the construction field. A questionnaire was designed to define the probability of risk occurrence and their effects, also to define the level of their effects by multiplying the probability occurrence with the effects. Another questionnaire was designed to define the extent of the effects of the most important risks on each target of the project, and to specify the procedures applied as a response to the risks. The results of this research revealed that "the Inflation, price changes" and "the difference between contracted quantities and actual quantities " are seen as the most important risk, where the studied risks in this work affect the schedule more than any other project targets. Also the results showed that avoiding the risks at the construction stage is the most used action.
Construction projects are characterized as very complex projects. This is because of their uniqueness, dynamic political and economic circumstances, weather, long life of projects, fluctuations in resources prices, and changes of engineering require ment, etc. Therefore, construction projects are subject to a wide range of various risks, which in case these risks occur will have considerable impacts on projects objectives in terms of time, cost and quality. Therefore, there is a need to investigate these risks and their impacts on project objectives and parties. The Client is one of the most important party in any project, and it usually lacks to have a clear strategy and policy to deal and manage risks that affect its objectives. This study aims to produce a strategy to deal and manage risks during construction stage from the client's point of view. The construction stage is selected because it takes a long time of the project life and consumes the largest amount of project budget, and it highly affects the project success or failure. Data were collected, by utilizing both questionnaire and interview survey, from more than one hundred participants from construction companies, clients and other construction professionals. An SPSS17 and EXCEL software were used to treat the data to find correlation between different variables, means and standard deviations. Risks were ranked based on risk importance indicator. The results showed that the most important risk is 'delay of payment to contractors as agreed in the contract' and the lowest risk is 'changes of design during construction'. The study concluded that the client should be concerned to formulate a specialized team in risk management in order to assist him in decision making process and developing practical solutions for dealing with risks in the construction sector. Keywords: risk , risk management , Client , Construction projects .
This paper aims to identify key characteristics projects in reconstruction stage in order to assist decision makers to produce appropriate approach to manage those projects effectively. A list of characteristics that may exist in reconstruction projects were identified through intensive literature review and pilot study with various stakeholders involved in in reconstruction stage.
يندرج هذا العمل ضمن إطار تطوير البرمجيات , في سياق هندسة البرمجيات، يستخدم مصطلح منهجية تطوير برمجيات (بالإنكليزية Software development methodology) للتعبير عن إطار العمل المتبع لهيكلة و تخطيط و السيطرة على عملية تطوير نظام معلوماتي. من الأمثلة الشائ عة على منهجيات تطوير البرمجيات: الشلال و النماذج و التطوير المتزايد و التطوير الحلزوني و تطوير التطبيقات السريع و البرمجة القصوى. يمكن أن تتضمن المنهجية جوانب من بيئة التطوير و استخدام بعض منصات العمل (مثل المكتبات و الأدوات البرمجية).
The confiscated is a financial penalty, It is imposed as a general principle by a court judgment irrevocable according to a Syrian constitution and anti-terrorism Act, but for political reasons, and an exception to the general principle it was imp osed by a legislative decree during the sixth decade of the twentieth century in Syria . The confiscated money are one of the public treasury resources of the state. In spite of the Syrian legislator provided how the confiscated is imposed, but it did not provide for how to manage and invest the confiscated money, As a result, there were many public entities that participate in the management of these funds, and many Legal systems that are used in the management and investment of these funds, Which calls for intervention of the legislator to regulate this issue through a unified legal text that includes the financial and administrative system of confiscated money.
comments
Fetching comments Fetching comments
mircosoft-partner

هل ترغب بارسال اشعارات عن اخر التحديثات في شمرا-اكاديميا